Kelfield Appeal 6013074 Allowed on 4 November 2026: Inspector Accepts a Corrected Biodiversity Net Gain Assessment With No Recorded Second Walkover, What It Means for BNG Surveys and Ecology Evidence (November 2026)

The habitat survey covered the wrong area. That single mismatch, between the land an ecologist walked and the red line on the planning application, was enough for North Yorkshire Council to refuse a small equestrian scheme at Moor Farm, Kelfield, near Selby. On 4 November 2026 a Planning Inspector allowed the appeal, reference 6013074, after accepting a corrected biodiversity net gain assessment submitted during the appeal itself [1]. The decision is a useful study in how ecological evidence is tested, and how close this applicant came to losing.

Key Takeaways

  • The original biodiversity net gain assessment was based on a habitat walkover in August 2024 that did not match the application's red line boundary.
  • A corrected assessment was submitted in May 2026, during the appeal, but did not record whether the ecologist had revisited the site.
  • The Inspector visited on 19 October 2026 and found the site broadly consistent with the photographs and information in the revised assessment.
  • The council raised no further objection to the revised material and offered no evidence that the habitats had changed.
  • Permission was granted subject to the statutory biodiversity gain condition and a 30 year Habitat Management and Monitoring Plan.

What Was Proposed

The scheme was modest: a riding arena of 40 metres by 20 metres, the use of an existing agricultural building for equestrian and storage purposes, and a change of use of farmland to paddocks. It is tied by condition to the private use of the house at Moor Farm. Riding schools, livery, competitions and other commercial uses are excluded.

The principle of the development was not the main issue. According to the published report of the decision, the central question was biodiversity [1].

Where the Ecology Evidence Went Wrong

Biodiversity net gain depends on a reliable baseline. The ecologist records which habitats are on the site, how large they are and what condition they are in. Those figures go into the statutory metric. If the surveyed area does not match the development site, the baseline cannot be relied on, and neither can the predicted gain.

Here the 2024 walkover covered a boundary that did not align with the red line. When the corrected assessment arrived in May 2026, it reflected the right boundary, but the paperwork did not say whether a further site visit had taken place. As the report of the decision notes, that meant the original ecologist had not expressly confirmed the habitat types, extents and conditions for the corrected area.

Stage Date What happened
Habitat walkover August 2024 Survey area did not match the red line
Refusal Before the appeal Council refused on biodiversity grounds
Revised assessment May 2026 Correct boundary, no recorded second walkover
Inspector's site visit 19 October 2026 Site compared with photographs and revised data
Decision 4 November 2026 Appeal allowed with conditions

Why the Inspector Accepted the Biodiversity Net Gain Assessment

Three things came together.

First, the council accepted that the revised document had not been before its officers at the time of refusal, and it did not raise a fresh objection to it during the appeal.

Second, the Inspector did not simply take the document on trust. She compared what she saw on site with the photographs and information in the revised assessment and found the conditions broadly consistent.

Third, there was no substantive evidence that the habitat baseline had changed in a material way since 2024.

On that footing she treated the revised information as a reasonable evidential basis for assessing biodiversity. She was also satisfied that the general biodiversity gain condition could be discharged.

The reported decision is careful about its limits. It does not say that surveys can be skipped, or that an old survey will always do. A site that had visibly changed, or a council that disputed the habitat conditions, could easily have produced the opposite result.

What Still Has to Be Delivered

Winning the appeal does not finish the ecology work. The statutory biodiversity gain condition under Schedule 7A to the Town and Country Planning Act 1990 applies automatically. A Biodiversity Gain Plan must be approved before development starts.

The permission also requires a Habitat Management and Monitoring Plan. It must set out the habitat works, who is responsible for them, how they will be monitored and how they will be managed over 30 years. Evidence of completed habitat enhancements is required before the development proceeds.

The Inspector declined two conditions the council had suggested. A surface water drainage condition was unnecessary because separate consent from the internal drainage board is needed anyway. An external lighting condition was dropped because no external lighting was proposed.

Lessons for BNG Surveys and Ecology Evidence

This was an appeal won on evidence that could have been stronger. The practical points for applicants, planning agents and ecologists are clear.

  • Match the survey boundary to the red line before submission. Share the final site plan with the ecologist and check it again if the red line moves.
  • Record every site visit. Dates, surveyor names and conditions should be stated in the report. A missing line about a second walkover became the main risk in this appeal.
  • Have the ecologist confirm revisions. When a metric is recalculated for a new boundary, the report should say expressly that habitat types, areas and conditions have been checked.
  • Include dated photographs. They allowed the Inspector to test the assessment against what she saw.
  • Do not rely on an appeal to fix the baseline. This appellant had a council that did not object and a site that had not changed. Others may not.
  • Plan for delivery. The Biodiversity Gain Plan and the 30 year management plan are separate pieces of work that need to be budgeted for.

Expert Evidence in Ecology Appeals

An ecologist's report in a planning appeal is expert evidence in all but name. An Inspector will ask the same questions a court asks of any expert. What did the author actually see, and when? Does the conclusion follow from the recorded facts? Is anything assumed and not checked?

A biodiversity net gain assessment that answers those questions on its face is far less likely to be challenged. One that leaves gaps invites a refusal, even on a small scheme.

Frequently Asked Questions

Does this mean an old habitat survey is acceptable?
No. It was accepted here because the site was found to be broadly unchanged and the council offered no contrary evidence.

Can a corrected metric be submitted at appeal?
It was accepted in this case, but that is not guaranteed. It is safer to correct errors before the application is decided.

Is biodiversity net gain still required after an appeal is allowed?
Yes. The statutory condition applies and a Biodiversity Gain Plan must be approved before work begins.

Conclusion

The Kelfield appeal shows that a biodiversity net gain assessment stands or falls on the reliability of its baseline. Applicants should confirm survey boundaries, insist on clearly dated survey records, and ask their ecologist to verify any revised metric on site. Getting that right at the start is far cheaper than arguing about it at appeal. This article is general information, not planning or legal advice.