Slough Appeal 6011425 Dismissed on 8 October 2026: No Preliminary Bat Roost Assessment for an Unfinished Building, Yet the BNG Metric Survived, What It Means for Ecology Surveys (November 2026)

An unfinished building that is not airtight or watertight, with mature trees and a hedge close by, is exactly where a bat might roost. A two-home scheme in Slough proposed to demolish one without any bat survey. The Planning Inspector dismissed the appeal. In the same decision, the council's attack on the biodiversity net gain metric failed. The contrast is a useful guide to what ecological evidence is needed, and when [1].

Key Takeaways

  • Appeal 6011425 was dismissed on 8 October 2026 after the written representations procedure.
  • The lack of a preliminary ecological appraisal or preliminary bat roost assessment was a separate, independent reason for dismissal.
  • The Inspector found no exceptional circumstances to justify leaving the bat survey work to a planning condition.
  • The council's biodiversity net gain objection failed: the statutory metric and ecology report were adequate for the planning stage.
  • New drawings and a daylight report sent in during the appeal were not taken into account.

The Decision in Brief

The site is land to the rear of 5 to 9 Elliman Avenue, Slough. The proposal was to demolish an unfinished building and build two three-bedroom houses, one of three storeys and one of two, with parking and storage. Slough Borough Council had refused the application [1].

The Inspector's findings can be summarised as follows:

Issue Finding
Design and appearance Acceptable in a mixed street scene
Neighbours' daylight and outlook Harmful: a main reason for dismissal
Bats Not assessed: a separate reason for dismissal
Biodiversity net gain Council's objection rejected

On living conditions, the Inspector found a likely significant loss of daylight and sunlight to neighbouring windows and an overbearing outlook for two houses on Elliman Avenue. The scheme achieved about 14 metres of separation, against the 15 metres advised in the council's guidance.

Why the Missing Bat Survey Was Fatal

The council's officer report had flagged the risk. The existing building was unfinished and open to the elements, and there were mature trees and a hedge nearby. Even so, the application included no preliminary ecological appraisal and no preliminary bat roost assessment.

All bats in Britain are legally protected. The Inspector could not be satisfied that demolition and redevelopment would avoid harm to them, because nobody had established whether bats were present.

The appellant might have hoped for a condition requiring a survey before work started. The Inspector found no exceptional circumstances to justify that. The general rule is that the presence or absence of a protected species, and the effect on it, must be known before permission is granted.

A condition can secure mitigation once the impact is understood. It cannot stand in for finding out whether there is an impact at all.

Why the BNG Metric Survived

The outcome on biodiversity net gain was different. The appellant had supplied a statutory biodiversity metric and a report from an ecological practice.

The council raised two points:

  1. That an existing hedgerow had been left out of the baseline.
  2. That the biodiversity gain hierarchy had not been properly followed.

The report and site photographs described bramble vegetation, not an identifiable hedgerow. The Inspector saw the same on the site visit. With no evidence of a wrongly excluded hedge, the metric was not undermined.

The Inspector was also satisfied that the information was adequate for the planning stage. The gain objective and the hierarchy could be dealt with through the statutory biodiversity gain condition, under which a Biodiversity Gain Plan showing at least a 10 per cent gain must be approved before development begins.

The lesson is that the habitat baseline was believed because it was evidenced. Photographs and a written description matched what the Inspector saw on site.

Late Evidence Did Not Rescue the Appeal

During the appeal the appellant submitted revised drawings and a daylight and sunlight report. The council had never seen them when it made its decision, and neighbours had not been consulted on them.

Applying the Planning Inspectorate's procedural guide, the Inspector declined to take them into account and decided the appeal on what had been submitted with the application.

The same risk applies to ecology. A bat survey commissioned after refusal may come too late to be considered, and survey seasons add further delay.

Practical Lessons for Small Sites

  • Commission a preliminary ecological appraisal before applying wherever buildings, trees or hedges are affected.
  • Add a preliminary roost assessment for any building to be demolished or altered, however new or unfinished it looks. Gaps and unsealed openings matter more than age.
  • Plan for the season. If the roost assessment finds potential, emergence surveys are generally needed in the active season, roughly late spring to early autumn.
  • Do not confuse a bat survey with BNG. They answer different legal questions. Passing one does not satisfy the other.
  • Evidence the habitat baseline. Dated photographs and clear habitat descriptions protect the metric from challenge.
  • Front-load the evidence. Assume that anything not in the application may not be admitted on appeal.

Ecological Expert Evidence at Appeal

Where an appeal turns on ecology, the ecologist's report is expert evidence in all but name. It should set out the survey methods, dates, conditions and limitations. It should state plainly what was and was not found. And it should be the ecologist's own professional opinion, not an argument for the client.

Here, a short piece of ecological work on the hedgerow point succeeded because it was factual and could be checked on site.

Frequently Asked Questions

Can a bat survey be left to a planning condition?
Only in exceptional circumstances. The Inspector found none here.

Does an unfinished building need a bat survey?
It may. A structure that is not sealed can offer access and shelter. A preliminary roost assessment will answer the question.

Did the scheme fail on biodiversity net gain?
No. The Inspector accepted the metric and left the detail to the statutory condition.

Is a small site exempt from protected species rules?
No. The size of the scheme does not reduce the duty to assess protected species.

Conclusion

Appeal 6011425 shows that a sound BNG metric will not save a scheme that has skipped a bat survey. Applicants on small sites should commission a preliminary ecological appraisal and roost assessment before submission, and keep clear baseline evidence. This article is general information only and is not legal or planning advice.