Croydon Appeal 6011675 Allowed on 20 November 2026: Inspector Rules a Bat Survey Was Not Needed to Validate an Application, What It Means for Ecology Surveys and Preliminary Ecological Appraisals (November 2026)

A council refused even to register a planning application until it received updated bat surveys and a preliminary ecological appraisal. On 20 November 2026 a Planning Inspector decided the application had been valid all along, and granted outline permission. The Croydon decision, appeal reference 6011675, is a rare ruling on bat survey planning validation, and it is as notable for what it does not say as for what it does [1].

The account below is based on the report of the decision published by Planning Geek on the day it was issued. Readers relying on the detail should read the decision letter itself.

Key Takeaways

  • The Inspector found the application was submitted with sufficient information to be determined and was valid, despite the absence of updated bat surveys at submission.
  • The council relied on a local validation list adopted in May 2026, after the application was lodged in April 2026.
  • Protected species were still treated as a genuine material planning consideration.
  • Updated bat surveys carried out during 2026 recorded foraging activity, and mitigation was addressed before permission was granted.
  • Both sides applied for costs and both applications were refused.

What happened at 275 Addiscombe Road

The application sought outline permission for a four-storey building with roof accommodation containing nine residential units at 275 Addiscombe Road, Croydon. Layout and scale were for approval. The reasoning treated the proposal as nine HMO rental units with shared kitchens and recreation space [1].

Croydon Council declined to validate the April 2026 application because it wanted updated bat survey evidence and a preliminary ecological appraisal. The applicant served a notice under Article 12 of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the formal route for challenging a validation requirement [2]. The council maintained its position, a non-validation notice was confirmed on 13 May 2026, and the applicant appealed against non-determination.

Inspector L Francis then had two questions to answer: was the application valid, and should permission be granted?

Why the Inspector found the application valid

Three strands of reasoning are reported.

The validation list post-dated the application. The council relied on a local list adopted in May 2026. The application was submitted in April. The council did not produce the list that applied at the earlier date, so its reliance on the May list was uncertain.

The planning history was unusually extensive. Several live permissions for redevelopment of the site already existed, including permissions granted in April 2026, and a separate appeal for 19 flats had been allowed on 21 September. The most recent permission had secured updated ecological and bat evidence through pre-commencement conditions. The Inspector found no convincing reason why this application should be treated differently at the validation stage.

Existing evidence and national guidance. The earlier ecological survey dated from 2021, and the Inspector accepted it could not be assumed to describe the position indefinitely. Even so, the available evidence, the previous decisions and the approach to further surveys in Circular 06/2005 supported an assessment of the application [3]. It had been submitted with "sufficient information to enable it to be determined and was valid".

What the decision does not say

It would be a mistake to read this as permission to skip ecology work.

The outcome is not a general right to avoid surveys for protected species. It is a case-specific finding about when the information had to be supplied.

The Inspector accepted that protected species were a material planning consideration. Updated bat surveys were in fact carried out during 2026. They recorded foraging activity, and mitigation was considered as part of the planning assessment. A signed unilateral undertaking was supplied during the appeal. Permission was granted subject to conditions, with ecology among the matters assessed.

In short, the surveys were done. The dispute was about timing.

Bat survey planning validation: the stage matters

Stage Question Typical ecology input
Validation Is there enough information to register and consider the application? Whatever the published local list reasonably and proportionately requires at the date of submission
Determination Is there enough information to decide it lawfully? A preliminary ecological appraisal and any further surveys needed where there is a reasonable likelihood of protected species being present and affected
Conditions What must be done before or during development? Updated surveys, mitigation and licensing where appropriate

Circular 06/2005 says that the presence of protected species, and the extent to which they may be affected, should be established before permission is granted, and that surveys should be left to conditions only in exceptional circumstances [3]. The Croydon site was unusual because of its run of recent permissions and existing survey evidence. Most sites will not have that history.

Lessons for applicants, councils and ecologists

  1. Check the list in force on the day of submission. A validation requirement adopted later cannot simply be applied backwards.
  2. Commission a preliminary ecological appraisal early. It is the quickest way to find out whether bat surveys are needed, and to avoid a validation argument altogether.
  3. Remember the survey season. Bat emergence and activity surveys are seasonal. An application lodged without them can be delayed for months if they are later required.
  4. Keep survey data current. A 2021 survey was accepted here as a starting point, not as a permanent answer.
  5. Use Article 12 where a requirement is unreasonable. It is a formal route, but it does not remove the need to address the planning merits.
  6. Councils should be consistent. The Inspector noted that the applicant had been treated differently from the approach taken on other permissions for the same site.

Expert ecological evidence at appeal

Planning appeals are decided on evidence, and ecology is no exception. The reported reasoning turned on what surveys existed, when they were done, what they found and how mitigation would be secured. An ecologist's report that sets out method, survey dates, limitations and conclusions clearly will carry weight with an Inspector in the same way that any expert evidence does. One that is out of date, or silent on its limitations, invites exactly the kind of dispute seen in Croydon.

The costs decisions

The developer sought a full award of costs against the council for unreasonable behaviour. The council sought a full award against the developer, arguing that supplying the ecology material at validation would have avoided the appeal. Both were refused.

The Inspector considered that deciding when surveys are required involves planning judgement, that the council had explained its position, and that the developer would have had to deal with the planning merits in any event. Equally, the applicant was entitled to challenge the council's approach through a statutory appeal.

Frequently Asked Questions

Can a council refuse to validate an application without a bat survey?

It can require information on its published local list where that is reasonable and proportionate. In this case the Inspector found the application was valid without the updated surveys.

Does this mean bat surveys are optional?

No. Updated bat surveys were carried out in 2026 and informed the decision. The ruling concerns the validation stage only.

What is a preliminary ecological appraisal?

An initial assessment of a site's habitats and its potential to support protected species, used to decide whether further surveys are needed.

What is an Article 12 notice?

A notice an applicant can serve on the local planning authority to dispute a validation requirement, which can lead to an appeal if the authority does not agree [2].

Conclusion

The Croydon decision confirms that validation requirements must be tied to the rules in force at submission and applied proportionately. It also confirms that protected species evidence remains essential before permission is granted. Applicants should obtain a preliminary ecological appraisal before submitting, plan bat surveys around the season, and keep ecological data up to date. This article is general information based on a published report of the decision and is not legal or planning advice.

References

  1. Croydon validation appeal allows nine HMO units, Planning Geek, 20 November 2026. planninggeek.co.uk.
  2. Town and Country Planning (Development Management Procedure) (England) Order 2015, Article 12, legislation.gov.uk. legislation.gov.uk.
  3. Circular 06/2005: Biodiversity and geological conservation, statutory obligations and their impact within the planning system, GOV.UK. gov.uk.