Last updated: 11 August 2026
Quick Answer: From 6 August 2026, SI 2026 No. 790 introduced a new exemption for development sites of 0.2 ha or less, but only where no priority habitat is present or affected. If your site contains or directly impacts any Section 41 priority habitat, the exemption does not apply and full 10% biodiversity net gain is required. A Phase 1 or UKHab preliminary habitat appraisal is now the document that determines which category your site falls into.
Key Takeaways
- SI 2026 No. 790 came into force on 6 August 2026, creating a 0.2 ha small-site BNG exemption for England [6]
- Priority habitat presence is the single gatekeeper, one qualifying habitat on site removes the exemption entirely [4]
- The exemption covers development footprint within the red-line boundary, not the wider landholding
- Commonly missed priority habitats on small urban and self-build plots include hedgerows, ponds, traditional orchards, and semi-improved grassland
- A Phase 1 / UKHab preliminary habitat appraisal is now the critical first document for any small-site application
- The former self-build and custom-build exemption has been removed for new applications under the revised rules [7]
- Transitional arrangements protect existing permissions granted before 6 August 2026 [6]
- Natural England's Priority Habitat Inventory (PHI) is a useful screening tool but does not replace a site survey
- If your site is not exempt, the standard BNG hierarchy applies, including on-site delivery, off-site units, and statutory credits [5]
What Is the BNG Small-Site Exemption for Priority Habitats?
The BNG small-site exemption introduced by SI 2026 No. 790 allows certain minor developments to proceed without completing a full biodiversity metric assessment or securing a biodiversity gain plan. To qualify, a site must meet two conditions simultaneously: the development footprint must be 0.2 ha or less, and the site must not contain or impact any Section 41 priority habitat listed under the Natural Environment and Rural Communities Act 2006 [4].
Priority habitat is the hard stop. A site measuring 0.19 ha qualifies on size, but if it contains even a small patch of semi-improved grassland or a single hedgerow meeting the Hedgerows Regulations 1997 criteria, the exemption is void and full BNG obligations apply. This is the detail that has caught several applicants in the first week since the rules changed.
For a broader overview of how exemptions work across different development types, see the guide to exempt projects on Biodiversity Surveyors.
How Does the August 2026 BNG Update Change Small-Site Rules?
Before 6 August 2026, small-site BNG rules operated under a separate small-sites metric regime introduced alongside the main BNG mandate in February 2024. The August 2026 changes, delivered through SI 2026 No. 790 and confirmed in Defra's July 2026 blog post, restructure the exemption framework significantly [6].
Key changes include:
- New 0.2 ha size threshold for a blanket exemption, replacing the previous small-sites metric pathway for the smallest sites
- Removal of the self-build and custom-build exemption for new planning applications, self-builders are now subject to the same priority habitat test as any other applicant [7]
- Temporary developments of up to five years may still qualify for exemption, but only where no priority habitat is affected [2]
- De minimis provisions remain in place but are equally blocked by priority habitat impacts
- Transitional arrangements mean that applications already permitted before 6 August 2026 continue under the rules that applied at the time of permission [6]
The practical effect is that the priority habitat check has moved from a secondary consideration to the first question any small-site developer or ecologist must answer.
Do I Qualify for the BNG Small-Site Exemption?
A site qualifies for the small-site BNG exemption if, and only if, both of the following are true: the total development footprint within the red-line boundary is 0.2 ha or less, and no Section 41 priority habitat is present on or directly affected by the development [4].
Use this quick eligibility test:
- Measure the development footprint (not the whole plot if only part is being developed)
- Check Natural England's Priority Habitat Inventory at the Magic Map application
- Commission a Phase 1 / UKHab preliminary habitat appraisal to confirm or rule out priority habitats on the ground
- If both conditions are met, the site is provisionally exempt, confirm with your local planning authority
Common disqualifying scenarios:
- A 0.15 ha infill plot with a hedgerow running along the boundary (hedgerows are Section 41 priority habitat if they meet the qualifying criteria)
- A 0.18 ha self-build plot adjacent to a pond that would be within the zone of influence
- A 0.2 ha brownfield site with remnant semi-improved grassland in a corner
What Size Site Qualifies for the BNG Small-Site Exemption?
The threshold is a development footprint of 0.2 ha or less, measured within the red-line boundary of the planning application [4]. This is not the total land area owned by the applicant, it is the area directly subject to development as defined in the application.
Important measurement rules:
- Phased developments cannot be artificially split to remain below 0.2 ha; the cumulative footprint applies
- Curtilage works (driveways, gardens, landscaping) count toward the footprint if they are within the red line
- Access roads and utility trenches within the red line are included
For context on how BNG applies to small development projects more broadly, the BNG for small development projects resource provides useful background.
How to Check If Your Site Has Priority Habitat BNG Status
Checking for priority habitat requires both a desk study and a physical survey. The desk study alone is not sufficient to claim exemption [1].
Step-by-step priority habitat check process:
- Run a Magic Map search using Natural England's Priority Habitat Inventory layer, this flags any mapped priority habitats within or adjacent to the site boundary
- Check the local authority's ecological constraints map if one is publicly available
- Commission a Phase 1 / UKHab preliminary habitat appraisal from a CIEEM-accredited ecologist, this is the definitive document for planning purposes
- Review hedgerow boundaries carefully, hedgerows qualifying under the Hedgerows Regulations 1997 are Section 41 priority habitat regardless of whether they appear on the PHI
- Assess ponds within 500 m, ponds that support or could support great crested newts or other priority species may trigger further assessment
- Document the findings in writing and retain the report for submission with the planning application
The PHI is a useful screening tool, but it is not exhaustive. Many small urban plots contain unmapped priority habitats, particularly hedgerows, ponds, and fragments of semi-improved grassland [1].
What Habitats Are Covered Under BNG Priority Habitat Rules?
Any habitat listed under Section 41 of the NERC Act 2006 can remove the small-site exemption. The following are the habitats most commonly encountered on small development sites and most frequently overlooked during early project scoping [1][2]:
| Habitat Type | Why It's Missed | Key Indicator |
|---|---|---|
| Hedgerows (S41) | Assumed to be "just a hedge" | Age, species count, connectivity |
| Traditional orchards | Not visible on aerial maps | Old fruit trees, lichen cover |
| Semi-improved grassland | Looks like rough grass | Wildflower diversity, soil type |
| Ponds | Seasonal; may appear dry | Marginal vegetation, depression |
| Ancient/veteran trees | Single trees overlooked | Girth, decay features, TPO status |
| Coastal/floodplain grazing marsh | Rural fringe sites | Proximity to watercourse, rush pasture |
Urban infill sites are particularly at risk of containing unrecorded hedgerows and ponds. Self-build plots on the edge of settlements frequently include semi-improved grassland that has not been intensively managed for decades.
BNG Small-Site Exemption Requirements August 2026: The Decision Checklist
Use this checklist before submitting a planning application claiming the small-site exemption. All boxes must be confirmed "yes" for the exemption to apply.
- Development footprint is 0.2 ha or less (measured within the red-line boundary)
- No Section 41 priority habitat is present within the development footprint
- No Section 41 priority habitat is directly affected outside the footprint (e.g., hedgerow removal, pond drainage)
- A Phase 1 / UKHab preliminary habitat appraisal has been completed by a CIEEM-accredited ecologist
- The appraisal confirms no priority habitat on or adjacent to the site that would be impacted
- The application was submitted after 6 August 2026 (transitional rules do not apply)
- The development is not a self-build or custom-build application relying on the former self-build exemption [7]
- The local planning authority has been notified of the exemption claim
BNG Small-Site Exemption vs Full Biodiversity Net Gain Requirements
If a site does not qualify for the exemption, the full BNG regime applies. This means a 10% net gain in biodiversity units must be demonstrated and secured for a minimum of 30 years [5].
| Factor | Exempt (0.2 ha, no priority habitat) | In-Scope (priority habitat present or >0.2 ha) |
|---|---|---|
| Metric assessment required | No | Yes (statutory biodiversity metric) |
| Biodiversity gain plan | No | Yes, approved by LPA |
| 30-year habitat management | No | Yes |
| Off-site units or credits | Not needed | May be required [see BNG off-site vs habitat banking] |
| Ecologist report | Recommended | Mandatory |
| Planning condition | No | Yes |
For sites that fall into full BNG scope, understanding what is in a biodiversity net gain assessment is the logical next step.
What Happens If My Site Doesn't Qualify for the Small-Site Exemption?
If priority habitat is confirmed, the site enters the standard BNG process. The developer must complete a full statutory biodiversity metric assessment, prepare a biodiversity gain plan, and secure the required 10% uplift through on-site habitat creation, off-site biodiversity units, or statutory credits as a last resort [5].
The BNG hierarchy requires on-site delivery to be explored first. Where on-site delivery is insufficient, off-site units purchased from a registered habitat bank can make up the shortfall. Statutory credits, purchased from Natural England, are the backstop option and are priced to incentivise genuine habitat creation over credit purchase.
For guidance on delivery options, see biodiversity net gain off-site or on-site delivery.
Common Mistakes with BNG Small-Site Exemption Applications
The most frequent error in the first week since SI 2026 No. 790 took effect is relying on the Priority Habitat Inventory alone without a ground survey [1]. The PHI does not capture all qualifying habitats, particularly hedgerows and small ponds on urban and peri-urban sites.
Other common mistakes:
- Assuming the former self-build exemption still applies, it does not for new applications submitted after 6 August 2026 [7]
- Measuring the whole plot rather than the development footprint, a 0.3 ha plot with a 0.18 ha footprint may still qualify if the undeveloped area is not affected
- Overlooking hedgerows on shared boundaries, a hedge on a neighbour's land that would be within the zone of influence of groundworks can still trigger the priority habitat test
- Not retaining the Phase 1 report, without a signed, dated appraisal from a CIEEM ecologist, the LPA may reject the exemption claim
Can I Appeal a BNG Priority Habitat Exemption Decision?
If a local planning authority disputes an exemption claim on priority habitat grounds, the developer can challenge this through the standard planning appeal process. There is no separate BNG exemption appeal route [4].
In practice, a well-evidenced Phase 1 / UKHab appraisal from a qualified ecologist is the most effective way to resolve a dispute before it reaches appeal. Where the LPA's ecological officer disagrees with the survey findings, a second opinion from an independent CIEEM-accredited ecologist or a pre-application meeting with the LPA ecology team is advisable.
FAQ
Q: Does the 0.2 ha threshold apply to the whole site or just the built footprint?
A: It applies to the development footprint within the red-line boundary of the planning application, not the total land area owned. Only the area directly subject to development is measured [4].
Q: I'm a self-builder, am I still exempt from BNG after August 2026?
A: No. The self-build and custom-build exemption has been removed for new applications submitted after 6 August 2026. Self-builders must now pass the same 0.2 ha and no-priority-habitat test as any other applicant [7].
Q: Can I rely on Natural England's Priority Habitat Inventory to confirm no priority habitat is present?
A: No. The PHI is a useful screening tool but is not comprehensive, particularly for hedgerows and small ponds. A Phase 1 / UKHab preliminary habitat appraisal by a CIEEM-accredited ecologist is required to confirm exemption eligibility [1].
Q: My planning permission was granted before 6 August 2026. Do the new rules apply?
A: No. Transitional arrangements mean that permissions granted before 6 August 2026 continue under the rules that applied at the time of permission. The new exemption rules apply to applications submitted after that date [6].
Q: What if only a small part of a hedgerow is within the red line?
A: If any Section 41 priority habitat is present within or directly affected by the development, the exemption does not apply regardless of the proportion affected. There is no de minimis threshold for priority habitat within the exemption test [4].
Q: How long does a Phase 1 / UKHab appraisal take to commission?
A: Typically two to four weeks from instruction to final report, depending on ecologist availability and site complexity. Seasonal constraints may apply for certain habitats. Commissioning early in the pre-application stage avoids delays to the planning programme.
Conclusion
Five days after SI 2026 No. 790 took effect, the priority habitat check has become the most consequential step in any small-site BNG assessment. The 0.2 ha exemption is genuinely useful for straightforward urban infill plots, but it is conditional, and the condition is one that catches sites where hedgerows, ponds, traditional orchards, or semi-improved grassland are present.
Actionable next steps for this week:
- Measure the development footprint accurately against the red-line boundary
- Run a Magic Map PHI check as a first screen
- Instruct a CIEEM-accredited ecologist to complete a Phase 1 / UKHab preliminary habitat appraisal before submitting the application
- If priority habitat is confirmed, begin the full BNG metric assessment process promptly to avoid programme delays
- If exempt, retain the appraisal report and notify the LPA clearly in the application documents
For developers who want to understand the full BNG process before commissioning surveys, the guidance for developers resource provides a structured starting point.
.bng-checker{font-family:Arial,sans-serif;max-width:520px;margin:0 auto;background:#f8f9fa;border:1px solid #dee2e6;border-radius:8px;padding:20px;}
.bng-checker h2{font-size:1.1rem;color:#1a3c5e;margin:0 0 12px;}
.bng-checker p{font-size:.9rem;color:#444;margin:0 0 14px;}
.bng-q{margin-bottom:14px;}
.bng-q label{font-size:.9rem;font-weight:600;color:#333;display:block;margin-bottom:6px;}
.bng-q select,.bng-q input[type=number]{width:100%;padding:7px 10px;border:1px solid #adb5bd;border-radius:5px;font-size:.9rem;box-sizing:border-box;}
.bng-btn{background:#1a3c5e;color:#fff;border:none;padding:10px 22px;border-radius:5px;font-size:.95rem;cursor:pointer;width:100%;}
.bng-btn:hover{background:#2a5a8e;}
.bng-result{margin-top:16px;padding:14px;border-radius:6px;font-size:.9rem;display:none;}
.bng-exempt{background:#d4edda;border:1px solid #28a745;color:#155724;}
.bng-inscope{background:#f8d7da;border:1px solid #dc3545;color:#721c24;}
.bng-result strong{display:block;margin-bottom:6px;font-size:1rem;}
BNG Small-Site Exemption Eligibility Checker (August 2026)
Answer three questions to get a provisional result under SI 2026 No. 790. Always confirm with a qualified ecologist.
— Select —
No priority habitat identified
Priority habitat present or affected
Not yet checked
— Select —
Standard minor development
Self-build / custom-build (new application post-6 Aug 2026)
Temporary development (up to 5 years)
Permission granted before 6 August 2026
function bngCheck(){
var sz=parseFloat(document.getElementById(‘bng-size’).value);
var ph=document.getElementById(‘bng-ph’).value;
var tp=document.getElementById(‘bng-type’).value;
var r=document.getElementById(‘bng-result’);
r.style.display=’block’;
r.className=’bng-result’;
if(!sz||!ph||!tp){r.className+=’ bng-inscope’;r.innerHTML=’IncompletePlease answer all three questions.’;return;}
if(tp===’existing’){r.className+=’ bng-exempt’;r.innerHTML=’Transitional rules applyYour permission predates 6 August 2026. Previous BNG rules continue to apply. Confirm with your LPA.’;return;}
if(ph===’unknown’){r.className+=’ bng-inscope’;r.innerHTML=’Survey requiredPriority habitat status is unconfirmed. Commission a Phase 1 / UKHab appraisal before claiming exemption.’;return;}
if(ph===’yes’){r.className+=’ bng-inscope’;r.innerHTML=’Not exempt, full BNG appliesPriority habitat is present or affected. A full statutory biodiversity metric assessment and gain plan are required regardless of site size.’;return;}
if(sz<=0.2&&ph==='no'){r.className+=' bng-exempt';r.innerHTML='Provisionally exemptSite meets the 0.2 ha threshold and no priority habitat is indicated. Retain the Phase 1 report and notify your LPA. Self-builders: note the self-build exemption no longer applies, this result assumes standard development.’;return;}
r.className+=’ bng-inscope’;r.innerHTML=’Not exempt, full BNG appliesDevelopment footprint exceeds 0.2 ha. A full BNG assessment is required.’;
}
References
[1] Biodiversity Net Gain Changes 6 August 2026 Small Site Exemption What Developers And Ecologists Need To Know – https://biodiversitysurveyors.com/blog/biodiversity-net-gain-changes-6-august-2026-small-site-exemption-what-developers-and-ecologists-need-to-know
[2] New Bng Rules And Exemptions Apply From The 6th August 2026 – https://www.tunley-environmental.com/en/insights/new-bng-rules-and-exemptions-apply-from-the-6th-august-2026
[4] Biodiversity Net Gain Exempt Developments – https://www.gov.uk/guidance/biodiversity-net-gain-exempt-developments
[5] Understanding Biodiversity Net Gain – https://www.gov.uk/guidance/understanding-biodiversity-net-gain
[6] Biodiversity Net Gain Amendments And Transitional Arrangements Published – https://defraenvironment.blog.gov.uk/2026/07/14/biodiversity-net-gain-amendments-and-transitional-arrangements-published/
[7] Bng Changes 6 August 2026 Small Site Exemption What Every Developer And Planner Must Know Now – https://biodiversitysurveyors.com/blog/bng-changes-6-august-2026-small-site-exemption-what-every-developer-and-planner-must-know-now