A wetland designed to sell biodiversity units was refused planning permission because the council could not tell whether it would work as a biodiversity gain site. The HMMP was missing. On 24 November 2026 a planning inspector allowed the appeal, but refused the appellant's claim for costs on the same day [1][2]. Both halves of that result carry lessons for ecologists and BNG surveyors.
Key Takeaways
- Appeal ref 6011455 concerned a wetland on about 6.1 hectares of farmland near Crewkerne, Somerset.
- The scheme was meant to act mainly as a biodiversity gain site and also as a phosphate credit bank.
- The application had an ecological impact assessment, a BNG strategy and a management plan, but no Habitat Management and Monitoring Plan (HMMP).
- A draft HMMP and a section 106 unilateral undertaking, supplied at appeal, gave the inspector enough certainty.
- Costs were refused because the council had acted reasonably on what was in front of it.
What Was Proposed?
The appeal was Taylor Wimpey UK Limited v Somerset Council. It was decided by Inspector H Nicholls on written representations, after a site visit on 3 November 2026 [1].
The site is around 1.2 km east of Crewkerne, where the Viney Brook meets the River Parrett. Its northern part lies in Flood Zones 2 and 3.
The proposal was an integrated constructed wetland, with an intake and outtake to the Viney Brook, earthworks and landscaping. It had two jobs:
- To work mainly as a Biodiversity Gain Site (BGS), often called a habitat bank.
- To act as a credit bank for phosphate nutrient credits, linked to the Somerset Levels and Moors Ramsar site downstream.
Why the Biodiversity Gain Site HMMP Mattered
The main issue was simple. Was there enough information to show the scheme would operate as a biodiversity gain site?
That question had a legal edge. The inspector noted that creating a biodiversity gain site is exempt from the statutory biodiversity gain condition. But if the site would not in fact work as one, the development would itself have to deliver biodiversity net gain.
The application came with:
- an Ecological Impact Assessment (EcIA), including a BNG Strategy
- a Landscape and Ecology Management Plan (LEMP)
It did not come with an HMMP. The appellant said the site, or its management, would pass to a specialist provider, and offered to secure the HMMP later.
Somerset Council's BNG Guidance Note of February 2024 lists an HMMP as something to be submitted with an application for a biodiversity gain site. The inspector said the note does not have the force of legislation or development plan policy. But it is clear about the level of detail the council expects.
What Changed at Appeal?
By the time the inspector decided the case, the appellant had added three things:
| Document | What it did |
|---|---|
| Draft HMMP | Showed how habitats would be created, managed and monitored |
| Revised LEMP with BNG metric information and the EcIA | Appended to the legal undertaking |
| Section 106 unilateral undertaking dated 7 July 2026 | Bound the owner and successors to deliver the scheme |
The undertaking requires the owner and any successors to:
- submit an HMMP for approval
- carry out the works
- register the land on the Biodiversity Gain Site Register
- allocate BNG and phosphate credits through agreed processes
- monitor and report
- allow the council to step in
- recalculate BNG or phosphate capacity when required
The inspector found that, even though there was still no fully approved HMMP, there was now sufficient certainty. The inspector also said that a planning condition alone would not have been a suitable way to secure the BNG and biodiversity gain site objectives.
The appeal was allowed. Conditions cover the flood risk assessment, the design of the offtake weir, an updated Water Environment Regulations assessment, a construction ecological management plan, construction drainage and landscaping. Informatives mention an eel pass under the Eel Regulations 2009 and biosecurity for invasive species.
The decision gives no biodiversity unit or phosphate credit figures.
Why Costs Were Refused
The appellant asked for its appeal costs from the council. The inspector said no [2].
When the council decided the application, there was not enough information to confirm that the site was suitable as a habitat bank. The council's judgement at that point was reasonable. The fact that better evidence arrived later did not make the refusal unreasonable.
Evidence that only becomes adequate at appeal can win the permission. It will not win the costs.
Lessons for Ecologists and BNG Surveyors
Submit at least a draft HMMP with the application
An EcIA, a BNG strategy and a LEMP were not enough for this council. Where local guidance asks for an HMMP, provide one at the outset, even in draft. Check each planning authority's own BNG guidance note before scoping the work.
Use a legal agreement, not just a condition
The inspector was clear that a condition alone would not do. A section 106 agreement or unilateral undertaking is the right tool to secure long-term management, register entry, monitoring and step-in rights.
Dual-use banks need clear accounting
Where one site sells both BNG units and nutrient credits, there must be an agreed process for allocating each and for recalculating capacity. Baseline and habitat condition data should be recorded so that they can be re-run.
Cover the related consents
Eel passage, biosecurity and water environment assessments were all flagged. Ecology reports for wetland schemes should deal with them from the start.
Ecology Reports as Expert Evidence at Appeal
A planning appeal is a form of dispute. The ecologist's reports are the expert evidence. Three points follow from this decision.
- Be complete at the outset. The decision-maker is judged on what was before it at the time.
- Be auditable. Metric inputs, habitat areas and condition assessments should be traceable to survey data.
- Be clear about what is still to come. If a plan will be finalised later, say what it will contain and how it will be secured.
Ecologists giving evidence should also keep their opinions objective and within their field, as any expert must.
Frequently Asked Questions
What is a biodiversity gain site?
It is land where habitats are created or enhanced so that biodiversity units can be sold to developers who need off-site gains. It must be legally secured and entered on the Biodiversity Gain Site Register.
What is an HMMP?
A Habitat Management and Monitoring Plan sets out how habitats will be created, managed and monitored over the long term, and who is responsible.
Is an HMMP always required with a planning application?
Not as a matter of national law in every case. But some councils, such as Somerset, ask for one in their own guidance for habitat bank proposals.
Why did the appellant win the appeal but lose on costs?
The evidence was strong enough by the appeal stage. It was not strong enough when the council made its decision, so the council had not behaved unreasonably.
Can the same land provide both BNG units and nutrient credits?
This scheme was designed to do both. The legal undertaking sets out processes to allocate each type of credit and to recalculate capacity.
Conclusion
The Crewkerne decision shows that a habitat bank can secure permission without a fully approved HMMP, provided a robust legal undertaking and a credible draft are in place. It also shows the price of leaving that work until the appeal.
For landowners and developers planning a biodiversity gain site, the next step is to commission the baseline survey, metric and a draft HMMP together, and to instruct solicitors on the legal agreement early. That is the surest way to avoid a refusal, an appeal and an unrecovered bill.
References
- Planning Inspectorate, Appeal Decision ref 6011455, Land at Higher Easthams Lane, Crewkerne, Somerset, 24 November 2026. appeal-planning-decision.service.gov.uk.
- Planning Inspectorate, Costs Decision ref 6011455, 24 November 2026. appeal-planning-decision.service.gov.uk.