Wakefield Appeal 6010809 Allowed on 19 November 2026: Inspector Removes Biodiversity Gain Conditions From a Retrospective Farm Building Permission, What It Means for BNG Surveys and Ecology Evidence (November 2026)

A planning inspector has removed two ecology conditions from a retrospective permission for a farm building near Wakefield, finding that the statutory biodiversity gain requirement was never brought into force for development authorised after the event. The decision, dated 19 November 2026, has already been widely discussed among planners and ecologists. It needs to be read carefully, because it decides less than some headlines suggest.

This article sets out what was decided in appeal reference 6010809, as reported in the Planning Geek appeal summaries published on 20 November 2026, and what it means in practice for landowners, farmers and anyone commissioning Biodiversity Net Gain (BNG) or protected species surveys.

What the appeal was about

The site is Chevet Levels Farm, Wakefield. A livestock feed store had been built to different dimensions from those in an earlier agricultural prior notification. Wakefield Council then granted retrospective planning permission under section 73A of the Town and Country Planning Act 1990, which is the provision that allows permission to be granted for development already carried out.

The council attached two conditions that the owner challenged:

  • Condition 2 required a Biodiversity Gain Plan.
  • Condition 3 required habitat creation, grassland, protection from public access, nesting features and bat roosts.

The owner applied to remove both. The council resisted, arguing that removal would leave ecological harm unaddressed and that no measurable gain would be secured. Inspector J Smith allowed the appeal.

Why the conditions were removed

The statutory BNG point

Mandatory BNG operates through a general biodiversity gain condition imposed by Schedule 7A to the 1990 Act. The inspector found that the relevant provisions were never commenced for development authorised under section 73A. He read regulation 2(2) of the Environment Act 2021 (Commencement No. 8 and Transitional Provisions) Regulations 2024 as excluding retrospective permissions of that kind.

The council had relied on the list of exemptions in the Biodiversity Gain Requirements (Exemptions) Regulations 2024, pointing out that retrospective development is not on it. The inspector treated that as the wrong starting point. If the requirement does not apply in the first place, the absence of an exemption is beside the point.

The local policy point

The council also relied on its local plan policies on biodiversity. The inspector found no evidence of harm to ancient woodland, veteran trees, irreplaceable habitat or a designated site. Reading those policies alongside current national policy, which restricts local requirements that go beyond statutory BNG, he held that the conditions were unnecessary.

Conditions 2 and 3 were removed. A revised plans condition was kept.

What the decision does not mean

The reported decision is specific to its facts, and three limits are worth stating clearly.

  1. It does not bar all ecological conditions on retrospective permissions. Where there is evidence of actual harm to habitats or species, a council may still be able to justify a condition under local and national policy.
  2. It does not require anyone to remove ecological work already carried out.
  3. It gives no immunity from wildlife legislation. Bats and their roosts, nesting birds, great crested newts and other protected species remain protected by law whether or not a planning condition mentions them.

Appeal decisions are also not binding precedent. Another inspector, or a court, could take a different view of the commencement regulations. Anyone tempted to build first and apply later in order to sidestep BNG is taking a significant planning and enforcement risk for an uncertain benefit.

The costs application and why baseline evidence matters

The owner also applied for an award of costs against the council. That application was refused.

One detail is instructive. The appellant had suggested that the habitat baseline was zero. An earlier metric calculation had shown 1.06 habitat units, and no updated calculation was produced to support the lower figure.

That is a reminder of how BNG evidence works. The statutory biodiversity metric starts from a baseline: the habitats present on the site before development, classified by type, measured by area or length, and scored for distinctiveness, condition and strategic significance. The result is expressed in biodiversity units. Every later figure, including the gain required, flows from that baseline.

An assertion that a site is worth nothing in habitat terms will not be accepted without evidence. A baseline habitat survey and a completed metric, prepared by a competent ecologist, is what a decision-maker expects to see. Where development has already taken place, the baseline may have to be reconstructed from earlier surveys, aerial imagery and site records, which is harder and more open to challenge.

Protected species surveys are a separate matter

BNG is about habitats and measurable units. Protected species are dealt with separately, and this decision does not change that.

A farm building, particularly an older one, may hold bat roosts or nesting birds such as barn owls and swallows. Ponds and rough grassland nearby may support great crested newts or reptiles. Disturbing these species or damaging their breeding or resting places can be a criminal offence. Planning authorities are entitled to ask for survey information before deciding an application, and survey seasons are fixed by the ecology of the species: bat activity surveys in the warmer months, great crested newt surveys in spring.

Expert evidence from ecologists at appeal

Ecology disputes at appeal are decided on evidence. Whether an appeal proceeds by written representations, hearing or inquiry, an ecologist's evidence is most persuasive when it is:

  • independent, giving an honest professional opinion and not simply advancing the client's case;
  • transparent about method, stating survey dates, weather, effort, limitations and the guidance followed;
  • complete, including the metric calculation and the condition assessments behind it;
  • consistent with professional standards, such as the good practice guidance published by the Chartered Institute of Ecology and Environmental Management.

The costs outcome here shows what happens when a figure is put forward without the calculation to back it.

Practical advice for farmers and landowners

  • Check before you build. If a building will differ from what was notified or approved, speak to the planning authority first.
  • Commission a baseline survey early. It is quicker and cheaper to record habitats before work starts than to reconstruct them afterwards.
  • Do not assume retrospective permission avoids ecology. Local policy and wildlife law still apply, and enforcement remains possible.
  • If conditions have been imposed on a retrospective permission, take planning and ecological advice on whether they are justified by evidence of harm.

How Biodiversity Surveyors can help

Biodiversity Surveyors carries out baseline habitat surveys, statutory metric calculations, Biodiversity Gain Plans and protected species surveys across England, and provides ecological evidence for planning applications and appeals.

Frequently asked questions

What did the inspector decide in appeal 6010809?

He allowed the appeal and removed two conditions, one requiring a Biodiversity Gain Plan and one requiring habitat and species measures, from a retrospective permission for a livestock feed store at Chevet Levels Farm, Wakefield.

Does mandatory BNG apply to retrospective planning permission?

The inspector found that the statutory biodiversity gain provisions were never commenced for development authorised under section 73A of the Town and Country Planning Act 1990. That is one inspector's reading and is not binding precedent.

Can I avoid BNG by building first and applying afterwards?

That would be unwise. Unauthorised development risks enforcement, local policies may still justify ecological conditions where there is evidence of harm, and wildlife legislation applies regardless.

Do I still need a bat survey for a farm building?

If there is a reasonable likelihood of bats being present and affected, yes. Protected species law is separate from BNG.

Why was the costs application refused?

The reported decision records that the appellant suggested a zero habitat baseline when an earlier metric showed 1.06 habitat units, and that no updated calculation was produced.

This article is general information, not legal or planning advice. Take specific advice on your own circumstances.